HIDDEN VILLAGE SEWER & WATER REPLACEMENT PROJECT
   
Updated: 10/04/2007 01:50:22 PM

Home
Shown below are tables and map views for the sewer and water system replacement work that will be done in Hidden Village this summer.  Each map shows how each system replacement (sewer and water) is broken into phases of work.  The "Road Closure" map will be updated weekly to show any areas within Hidden Village where the road is closed to traffic. The dates  shown in each table are estimates which will be updated as the project progresses.
IMPORTANT PROJECT NOTES:
Water Shut-offs:  For areas where water is scheduled for temporary shut-off, notices will be placed on the doors of individual units
at least 24 hours in advance.  NO NOTICE CAN BE PROVIDED FOR EMERGENCY SHUT-OFFS.  These occur when water lines are hit
during construction and the mainline valves must be turned off to make repairs.
 

  OVERALL CONSTRUCTION SCHEDULE 
 

       
Updated: 10/01/07     End of Day
         
Phase Estimated Start Estimated Completion % Complete
Date Date
Phase 1     100%
Phase 2 07/10/07 07/18/07 100%
Phase 3 07/19/07 07/24/07 100%
Phase 4 07/25/07 08/01/07 100%
Phase 5 08/02/07 08/11/07 100%
Phase 6 08/13/07 08/23/07 100%
Phase 10 09/05/07 09/10/07 100%
Phase 8 08/28/07 09/11/07 100%
Phase 7 09/10/07 09/14/07 100%
Phase 9 09/14/07 09/16/07 100%
Phase 11 09/21/07 09/29/07 29%
Phase 12 09/30/07 10/05/07 0%
Phase 13 10/06/07 10/08/07 0%
Phase 14 10/09/07 10/20/07 0%

 

       
 
WATER SCHEDULE      
         
Updated: 10/01/07 End of Day    
       
Phase Estimated Start Estimated Completion % Complete *Schedule
Date Date Factor
Phase 5 08/02/07 08/11/07 100% 2.0
Phase 6 08/13/07 08/23/07 100% 6.0
Phase 8 08/28/07 09/11/07 100% 17.0
Phase 9 09/14/07 09/16/07 100% 0.0
Phase 11 09/21/07 09/29/07 29% 0.6
Phase 12 09/30/07 10/05/07 0% N/A
Phase 13 10/06/07 10/08/07 0% N/A
Phase 14 10/09/07 10/20/07 0% N/A
       
       
*Schedule Factor is the number of days the contractor is ahead ( + ) or behind ( - ) schedule.
 
     
 

WATER SYSTEM PLAN VIEW AND CONSTRUCTION PHASING


 
SEWER SCHEDULE      
         
Updated: 10/01/07 End of Day    
       
Phase Estimated Start Estimated Completion % Complete *Schedule
Date Date Factor
Phase 1     100%  
Phase 2 07/10/07 07/18/07 100% 1.0
Phase 3 07/19/07 07/24/07 100% -3.0
Phase 4 07/25/07 08/01/07 100% 0.0
Phase 7 09/10/07 09/14/07 100% -9.0
Phase 10 09/05/07 09/10/07 100% -11.0
       
*Schedule Factor is the number of days the contractor is ahead ( + ) or behind ( - ) schedule.
 
SEWER SYSTEM PLAN VIEW AND CONSTRUCTION PHASING


Today's Date: 05/02/08